KUALA LUMPUR: The government has imposed a liquidated ascertained damages (LAD) penalty of RM31.8 million on two contractors for delays in completing the Sabah Pan Borneo Highway (LPB) project.
Deputy works minister Ahmad Maslan said 23 work packages were identified as running behind the original schedule of the mega infrastructure project.
“Several factors, including unpredictable weather, land acquisition challenges, utility relocation issues, and on-site contractor performance, caused the delays.